When buyers say “make it explosion-proof,” projects often derail because the requirement is not defined as an engineering scope. 

ATEX/IECEx compliance is not a single label on a control cabinet—it is a system-level requirement involving area classification, equipment selection, documentation, and verification.

For overall process design and scale-up logic, see Solvent Extraction Plant: Process & Scale-up 

What ATEX and IECEx are (and why buyers care)

  • ATEX is the EU framework for equipment and workplaces in explosive atmospheres (commonly referenced in Europe and many international projects).

  • IECEx is an international certification scheme used in many regions and often requested in global tenders.

In procurement terms, what matters is not the acronym—it’s whether your project requires:

  • hazardous area zoning (Zone 0/1/2 for gas; 20/21/22 for dust)

  • certified equipment categories and protection concepts

  • documents and verification acceptable to your inspector, EPC, or local authority

First decision: what is the hazardous area and where is it?

Most solvent extraction plants contain flammable vapor sources at:

  • extraction vessels (loading, venting, sampling, manways)

  • filtration units (especially if open discharge)

  • vacuum concentrator/evaporator and condensers

  • solvent receivers, storage tanks, transfer pumps

  • vent lines and any potential leak points

Buyer mistake #1: requesting “ATEX for the whole plant” without area zoning.
A correct scope begins with hazardous area classification—usually performed by the buyer’s EHS team or engineering consultant based on solvent type, ventilation, and operating scenarios.

Define “explosion-proof scope” as a list (the only way to quote accurately)

A reliable RFQ should specify which subsystems must comply. Typical ATEX/IECEx scope items include:

3.1 Electrical and instrumentation in hazardous zones

  • motors, junction boxes, cable glands

  • sensors (temperature, pressure, level), transmitters

  • solenoid valves, actuators

  • lighting, local panels (if installed in-zone)

3.2 Control system architecture

  • whether the PLC/HMI is located in safe area or hazardous area

  • barriers/isolators for signals from hazardous zones

  • emergency stop / interlocks / alarm philosophy

3.3 Mechanical risk controls (often overlooked)

  • grounding and bonding points for static electricity

  • conductive hoses and appropriate gaskets

  • pressure/vacuum protection devices (relief valves, rupture discs where applicable)

  • ventilation interfaces (ducting, extraction points)

  • inerting (N₂) if required by risk assessment

Buyer mistake #2: assuming mechanical items are “automatically ATEX.”
ATEX/IECEx risk control is as much about installation practice and system design as it is about the nameplate on a motor.

Which solvents trigger ATEX/IECEx attention?

Most common solvents in botanical/ingredient extraction that are typically considered flammable:

  • ethanol, IPA, acetone, ethyl acetate, hexane, etc.

If your process includes heated solvent, vacuum evaporation, or solvent storage/transfer, the case for hazardous area classification is stronger.

ATEX/IECEx is not only about the “equipment”—it’s also about documents

If your customer/EPC requests ATEX/IECEx, they usually expect a documentation package that may include:

  • certificates for in-scope components

  • equipment lists with Ex markings

  • wiring diagrams, loop diagrams (for in-zone instruments)

  • risk assessment or design basis notes (as applicable to supply scope)

  • manuals and maintenance instructions consistent with Ex requirements

  • FAT records and nameplate verification

Buyer mistake #3: asking for ATEX/IECEx but not defining what documents must be delivered, and who is responsible for site installation compliance.

Typical protection concepts you may see (buyers should recognize the language)

Depending on equipment type and zone, protection concepts can include:

  • flameproof enclosures, increased safety, intrinsic safety, pressurization, etc.

You don’t need to “choose the concept” in the RFQ, but you should specify:

  • hazardous zone classification

  • whether you require intrinsic safety for instruments

  • whether control cabinets must be in safe area

  • whether pressurization is acceptable for certain enclosures

Practical scope boundary: what the supplier can guarantee vs what the site must implement

A solvent extraction equipment supplier can typically guarantee:

  • certified components for the agreed scope

  • compliant control panel design for the scope

  • grounding/bonding provisions on skids

  • documentation and FAT verification for their supply

The site/EPC usually must handle:

  • area classification study (unless otherwise contracted)

  • installation compliance (cable routing, glands, earthing network, ventilation)

  • final inspection and authority acceptance

Clarifying boundaries prevents dispute and delays.

How to avoid the 5 most common ATEX/IECEx procurement failures

  1. No area classification provided → supplier guesses, quote becomes meaningless

  2. Scope not listed → “explosion-proof” becomes a marketing word, not a deliverable

  3. Control panel placed in-zone unintentionally → cost jumps late

  4. Documentation expectations unclear → rejection at inspection stage

  5. Open filtration chosen for solvent-heavy slurry → EHS problems and retrofits

If your plant filtration is not sealed, emissions control may drive zoning and cost. Read Filtration Options: Bag vs Filter Press vs Nutsche vs ANFD

RFQ checklist — what to send to get a correct ATEX/IECEx proposal

To receive a clear ATEX/IECEx scope and pricing, send:

  1. solvent(s) and operating conditions (temperature, vacuum, venting scenarios)

  2. hazardous area classification (zones, if available)

  3. which subsystems are in hazardous zones (motors, instruments, pumps, local panels)

  4. control system location (safe area vs hazardous area)

  5. required certificates/standards (ATEX, IECEx; any local requirements)

  6. documentation deliverables required by your customer/EPC

  7. site utilities and ventilation assumptions

  8. whether inerting is required by your internal risk assessment

Then size the whole line consistently using the hub RFQ: Solvent Extraction Equipment

FAQ

Q1: Can you make the entire line ATEX/IECEx?

Yes, but the correct approach is to define the hazardous zones and scope list. Over-scoping increases cost unnecessarily; under-scoping increases compliance risk.

They are related but not identical frameworks. What matters is what your customer and local authority accept and what documentation is required.

Ethanol is flammable; whether explosion-proof is required depends on zoning and local code. If you concentrate under vacuum and recover solvent, you should assume zoning will be reviewed.